Language:


The Standard Period Register - Example

This page uses an example to illustrate the use of the Standard Period register and the 'Apply Standard Period' Maintenance function. Please refer here for a description of this register and function.

---

The Calendar illustrated below shows a week's Profile Activities for Person FF:

We will use the Standard Period register and 'Apply Standard Period' Maintenance function to copy these Activities to the next three weeks. First, we will enter a record to the Standard Period register for the period 2/7/2018-8/7/2018 for Person FF:

The period runs for one calendar week from Monday to Sunday. This is necessary to avoid new Activities being created for weekends.

Next, we will use the 'Apply Standard Period' Maintenance function to copy these Activities to the next three weeks:

We have specified that 9/7/2018 is the day that will be used in the first new Activity. So, all Activities from Monday 2/7/2018 (the first date in the Standard Period record) will be copied to Monday 9/7/2018, all Activities from 3/7/2018 will be copied to 10/7/2018 and so on. This cycle will be repeated three times. This is the result:

---

The Standard Period register in Standard ERP:

Go back to: