Overview

Illustrated below is an example of the Overview version of the Project Invoicing report. The illustration shows a Project that will be invoiced on an "Actual" basis, and the report has been produced with the Inv. Trans. option selected. The report therefore contains an 'Invoiceable') section that summarises the Project Transactions that have not yet been invoiced. This section can contain up to four sub-divisions representing each cost type (time, purchases, materials and Stocked Items delivered from Sales Orders): three are shown in this example.

For each Item, a single line is shown with a total amount to be invoiced (in the Sum column). The amount budgeted for each Item is also shown.

The Downpay Invoiced figure shows that at least one Down Payment Invoice has been created, and the Downpay Invoiceable figure shows that another one is now scheduled for creation.

Clicking (Windows/macOS) or tapping (iOS/Android) on an Item Number opens a second window listing the Project Transactions featuring that Item. This is shown below. In addition (not shown), clicking on an underlined Budget figure opens the appropriate Budget record.

A further level of drill down is available from this list: click or tap on an Item Number or employee Signature to open a Project Transaction:

If necessary, you can edit the Project Transaction (e.g. you could add a Discount or Markup). After saving, recalculate the reports on the levels above to have the changes included (to do this, select 'Recalculate' from the Operations menu (Windows/macOS) or Tools menu (iOS/Android) in the report windows). This provides an extremely convenient and simple method to make final adjustments to Projects before invoicing.

The second section of the Project Invoicing report, entitled 'Invoice', shows the contents of an Invoice, were you to raise one at the time of producing the report. This section will be included in the report if you produce it using the Invoice option. It will include deductions for down payments that have already been invoiced. Each line in this section of the report represents a row as it would appear on the Invoice, following the rules set for the Project on the 'Time & Purchases', 'Stock & Materials' and 'Invoicing' cards. In this example, all four invoicing options are set to "by Items", so a single total invoiceable figure is shown for each Item:

You can create the Invoice from the report, using the [Create Project Invoices] text link at the top. This will open the specification window for the 'Create Project Invoices' Maintenance function, with the Project field already filled in with the Project Number or Numbers that you entered when producing the report:

Overview per Employee

Producing the Project Invoicing report with the Overview per Employee option selected will add detail to the 'Invoiceable' section while leaving the 'Invoice' section unchanged.

Where the Overview contained a single summary line for each Item used in uninvoiced Project Transactions, the Overview per Employee will contain a single summary line for each Item/Person combination:

If you use both Time Sheets and Activities for time recording, there may be two lines for each Item/Person combination, one for time recorded from Time Sheets and one for time recorded from Activities.

Detailed

Producing the Project Invoicing report using the Detailed option selected will again add detail to the 'Invoiceable' section while leaving the 'Invoice' section unchanged. In the Detailed version of the report, every uninvoiced Project Transaction will be listed individually.

Click or tap on an Item Number, employee Signature or Description to open the corresponding Project Transaction and on a Budget figure to open a Project Budget record.

As Budgeted

If a Project is to be invoiced on an "As Budgeted" basis, the 'Invoiceable' and 'Invoiced' sections of the report will both reflect the Project Budget if you produce the report before creating an Invoice. For an "As Budgeted" Project, there will not be much difference between the Overview, Overview per Employee or Detailed options: the 'Invoiceable' section in the report will always list uninvoiced Budget rows individually:

After creating the Invoice, the Project will be treated as fully invoiced unless you add to the Budget. As you carry work out on the Project. Project Transactions will still be created, to record the costs incurred, but they will never be invoiced. If you now produce the Project Invoicing report for the Project, these Project Transactions will be shown in the 'Invoiceable' section, but the report will not contain an 'Invoiced' section as the Project is fully invoiced.

If a Project is partly to be invoiced on an "Actual" basis and partly on an "As Budgeted" basis (for example. it might be that time is to be invoiced on an "As Budgeted" basis and Stocked Items on an "Actual" basis), this will be reflected in the Project Invoicing report. Every uninvoiced Project Transaction will be included in the 'Invoiceable' section, while only those that will be invoiced on an "Actual" basis will be included in the 'Invoice' section.

---