Entering a Production Order - Planned Time Card
- Days duration, Time duration
- These fields show how much time will be needed to complete the Production Order. This information is calculated from the Fixed Assembly Days, the Days, Hours, Minutes and Seconds to Produce and the Time to Setup recorded in the Recipe.
- The Buffer Days in the Production Settings setting and the relevant record in the Machine Hours register are not included when calculating the Days duration and the Time duration. Therefore, these fields show the actual work time required. The required calendar time including breaks could be longer.
- These fields will be updated each time you change the Qty in the header. You cannot change these fields.
---
In this chapter:
See also:
Go back to: